Proj 592 Proj1

In: Business and Management

Submitted By dck69
Words 334
Pages 2
The construction of the new theme park project is laid out for 180 days of construction to finish. This project has a start Date of Monday April 4, 2008. The preliminary cost is $4,449,920.00 and with a completion date of December 19, 2008. The theme park will include a Ferris wheel, Rope course, Climbing walls, Carousel, Bowling, Go carts, and a Mini golf. The desired walk through date is December 18, 2008 with a grand opening on December 19, 2008.
Executive Summary
It has been 6 months since the start of the project and we now have 40% of the tasks complete. The actual cost so far to date is $1,230,683.00. There are many of the scheduled tasks behind in this schedule. The entire project thus far is behind schedule with a work performance index of .66 and 12% behind schedule. There are corrective actions that can get this project beck on schedule at minimal cost. This project should not be abandoned and should continue forward with the support of the investors.
Schedule 1
The data is being supplied from MS Project. The WBS includes all work that has to be done to complete the project from start to finish. The current WBS includes all the data and baseline, review date and the current date is set to October 1, 2008. The project start date is April, 14, 2008. Nearly 6 months into the project it is set at 40% complete. This shows the project is behind schedule. The schedule variance is 5.98 days from the completion date. The new completion date is December 29, 2008 without any further changes. As of October 1,2008 the following task have been completed

The completed tasks are Site Layout & Site grading, Footings and foundations, Masonry, Frames, columns and beams, Slab on grade, HVAC Stacks & Vents, Electrical Boxes. There are also many completed tasks that are incomplete.
Attached is the WBS chart showing the dates on October 1, 2008.…...

Similar Documents

Premium Essay

Sec 592 It Governance

...Keller Graduate School | SEC 592 IT Governance | Assignment Week 2 | | The purpose of this essay to highlight the relationship between IT execution and IT governance. Within it, we will also cover the COBIT framework with regards to controlling IT associated risk. IT governance is about the way in which leadership accomplishes the delivery of important business capability using IT strategy, goals and objectives while adding business value and controlling risks. IT governance is concerned with strategic alignment between the goals and objectives of the business and the utilization of its IT resources to effectively achieve the desired results. In comparison, IT execution is the usage of sound management practices and the use of IT controls. These controls are usually based on a framework consisting of best practices that are used as guidelines to help successfully implement IT governance. For this discussion, we will focus on the Control Objectives for Information and related Technology (COBIT) Framework. The COBIT framework is a set guidelines that lay the groundwork for best practices that provide for the managing, auditing, and assistance of users, which allows them to measure their processes, and develop and improve the controls of a company. There are two major organizations that are associated with IT governance: ISACA (Information Systems Audit and Control Association) and the IT Governance Institute. Effective and efficient enterprise IT governance......

Words: 883 - Pages: 4

Premium Essay

Proj 1 Deamliner

...Development of the Boeing 787 Dreamliner Dararoth Rath DevRy University PROJ 595 Instructor: Willie Hosch 01/24/2013 Introduction In 2003 Boeing started a building concept called 7E7 prior to changing it 787 in 2005. The Boeing 787 project dreamliner is to build a 20% lighter plane due fully builds from composite material, latest in flight entertainment technology, ability to carry more passengers, larger over head bins, larger cargo space, increasing nautical miles in mid range aircraft the same class as Boeing 767 and a lowest cabin pressure of any planes in the air that provide the most comfort to passengers. We will be looking at two fault trees analysis for the Boeing 787 flight instrumentation failures. In the event that there is instrumentation failures inside Boeing 787 cockpit it can cost by loss of airspeed information which is fault tree one or by loss of advisory panel information which is fault tree two. Fault Tree One Fault Tree One Analysis The flight deck system for the Boeing 787 can fail but loss of cockpit instrumentation information which can be cause by loss of airspeed information. As can be seen in the fault tree in order for airspeed information to be loss the following three must occurs: Loss of Airspeed Indicator and RPM fails and Loss of Communication Information. If only 2 of the three or 1 of the three occurs then loss of airspeed information cannot occurs. In order for loss of airspeed indication system occurs only one of the......

Words: 506 - Pages: 3

Free Essay

Hr 592 Mini Paper

...Jeremy Pflug HR 592 Mini-Paper (Course Project) 2/10/12 I have decided to make the topic of my needs assessment the Lakota School District Transportation Department. I live in the Lakota School District and currently we are having a difficult time passing the newest school levy. I believe this will firmly impact the transportation department, as fuel has risen to an all time high and on top of that, bus drivers will be laid off and routes will be extended in order to fulfill the budget and need. With the advancements in technology, survey can completed quickly online. These surveys provide ample information regarding the district’s needs, how the people living in the district feel that cuts will affect the transportation department and ultimately will their children be safe with extended routes and less training for the bus drivers. A case study was done in 2006 by the Lakatos Group for the Ohio Department of Transportation Office of Transit. In this needs assessment, the underlines that inadequate transportation was being provided to many different counties throughout the state of Ohio. The need for transportation especially in rural areas was needed and that there was enough capital and operating funds to provide them with it. To view the case study: http://scopt.transportation.org/Documents/Intercity%20Bus%20Study%20Final.pdf In the analysis portions of my paper, I have been discussing many tasks that are needed in order to provide the proper training......

Words: 561 - Pages: 3

Premium Essay

Roj-592

...Lashelle D. Scott | 3620 Woodchase Drive Apt. #97 | Houston, Texas 77042 | 832-594-4535 | PROJ-592-11483 Project Cost & Schedule Control | Professor Erik Esser | May 12, 2013 | Lashelle D. Scott | 3620 Woodchase Drive Apt. #97 | Houston, Texas 77042 | 832-594-4535 | PROJ-592-11483 Project Cost & Schedule Control | Professor Erik Esser | May 12, 2013 | Project Definition, WBS, and Cost - You Decide Project Definition, WBS, and Cost - You Decide Project Definition, WBS, and Cost - You Decide Scenario VisionTec, an advanced technology company in the Midwest, is developing their new Vision System product for the lucrative Pharmaceutical Market. This system uses a high-resolution camera to inspect drug labels to ensure they contain the proper information to meet the ever evolving governmental standards. Your task is to organize the product development process for this revolutionary product which could save countless lives! Role You've just sat down with Marketing Director, Kara Rose, and R&D Director, Jessie Megana. After the standard pleasantries, Kara (well known to be focused on short meetings) starts with your marching orders Your task is to organize the product development process for this revolutionary product which could save countless lives. So, as Project Manager, you will create a Work Breakdown Structure (WBS) using the steps that Kara and Jessie have relayed during your meeting. Script Kara: The first......

Words: 995 - Pages: 4

Premium Essay

Proj 595 Week 5

...DeVry University Keller Graduate School of Management WEEK 5 make up assignment Submitted in Partial Fulfillment of the Course Requirements for Project Risk Management PROJ 595 November 29, 2013 To ensure that risks remains effectively managed throughout the project, ATOM provides a series of risk reviews. These risk reviews are major and minor risk reviews. Major risk reviews usually takes place at key points during the project, either at the beginning of a new phase or a significant milestone within a phase, but they do not happen enough to ensure that assessment of risk exposure remains current. Minor risk reviews on the other takes place in line with the normal reporting regime of the project. The ATOM major review aims to review all current risks and any other risk raised since the last formal review, identify new risks, update the risk register, produce a full report and periodic reporting information for the project progress reports and progress meetings, and check the effectiveness of current risk management process. The ATOM minor review on the other hand aims to review the most significant current risks, and all draft risks raised since the last formal review, identify new risks, update the risk register, produce a summary risk report and periodic reporting information for project progress reports and progress meetings. Post project review is conducted to create a body of knowledge and experience on which the project team can......

Words: 343 - Pages: 2

Premium Essay

Hrm 592

...Christopher House Training Report Damilola Matuluko HRM 592: Training and Development Professor Readus October 19, 2014. Table of Content Executive Summary……………………………………………………………………….3 Background………………………………………………………………………………. Organization…………………………………………………………………………….. Mission………………………………………………………………………………….. Goals…………………………………………………………………………………….. Values……………………………………………………………………………………. Needs Assessment design, Implementation and Analysis………………………………… Needs Assessment Design………………………………………………………………. Organizational Analysis………………………………………………………………… Person Analysis………………………………………………………………………… Task analysis…………………………………………………………………………… Training intervention…………………………………………………………………….. Training plan…………………………………………………………………………. Return on Investment and Cost-Benefit Analysis……………………………………….. Return on Investment Analysis…………………………………………………………. Cost Benefit Analysis……………………………………………………………………. Training evaluation Plan……………………………………………………………………. Before Training……………………………………………………………………………. After Training……………………………………………………………………………… Recommendations……………………………………………………………………………. References…………………………………………………………………………………….. Appendix A…………………………………………………………………………………… Appendix B…………………………………………………………………………………… Executive Summary This proposed document for......

Words: 4508 - Pages: 19

Premium Essay

592 Syllabus

...Business Combinations (FASB Nos. 160, 141R, etc.) Topic 815 Derivatives and Hedging (FASB Nos. 133; 138; 149; 155; 161, etc.) Topic 845 Nonmonetary Transactions (FASB No. 153, APB 29, etc.) Topic 860 Transfers and Servicing (FASB Nos. 156; 140, etc.) GRADING A letter grade will be determined based on the following: Points % Contribution to class learning (attendance , participation and presentations) 100 10% Homework and other minor assignments 150 15% Financial statement disclosure project 350 35% Other projects, cases and major assignments (may include an in-class simulation of comprehensive exam question) and other exams 400 40% 1000 100% How to Write-up a Case for Acct 592 How to start: Cases generally have questions at the end. Use these as GUIDES to the issues presented in the case. For example, you may not answer each question in the exact order presented if they are related and one paragraph would do for several answers. Or maybe the alternative you choose makes one or more issues irrelevant. Your task is to understand the FACTS of the case and then do your research. But the goal isn’t to find citations – the goal is to APPLY the accounting standards to the facts of the particular case. I don’t want long quotations – especially when all or part is not relevant to the case at hand. Your letter or memo is not an academic report intended to cover all issues. You want to concisely identify the......

Words: 2858 - Pages: 12

Free Essay

Obst 592 Exam Review

...OBST 592 Exam 3—Study Guide Thanks to Brian & Jung for their notes..I used both to complete this. Maybe it can be of some help for whoever hasn’t gotten a chance to fill it out. If there is something that says “I” it’s referring to Dr. Yates…Jung’s notes were transcribed, so its exactly what Dr. Yates said. If anything is wrong or should be added, please let me know  This test will cover the books of Zechariah, Joel, Malachi, Psalms, Proverbs, and Job. Some test questions will cover general knowledge of these books discussed in the class sessions on these books. The best way to prepare for these questions is to study through your notes from the class sessions covering these books. Zechariah: Know the three sections of the book: The night visions: The night visions (Zech 1:1-6:14) 1. The vision of the man among the myrtle trees (1:7-17) a. Angels of God going out to judge the other nations b. God will bring judgment against the nations who feel safe and secure 2. The vision of the four horns and the four craftsmen (1:18-21) a. The nations that harm Israel will be destroyed b. Craftsman will destroy horns 3. The vision of the man with a measuring line (2:1-12) a. Jerusalem will be bigger and better than ever before 4. The vision of the new garments for the high priest (3:1-10) a. Cleansing of the priest and the restoration of Israel’s worship b. Satan appears in this vision 5. The vision of the golden lampstand and the two olive trees (4:1-14) a.......

Words: 5772 - Pages: 24

Premium Essay

Course Project Proj 595

...Course Project Paper Part II Salvage CSS Georgia Branden Pevear Keller Graduate School of Management PROJ 595 Willie “Alex” Hosch 11AUG15 Table of Contents Table of Contents 2 Introduction 3 Decision Tree Analysis 3 Discussion of Decision Tree 3 References 7 Introduction The expanding of the shipping waterway in Savannah, Georgia, won't be dredging up just mud, silt, and sand, it will be raising up a link to the past: an “iron-sided” ship that secured the city of Savanah during the Civil War. That was until the ship was deliberately scuttled so it would not fall into Union military hands at the end of the war. The raising and removal of the CSS Georgia is an essential federal, and state proposal that includes the increasing the channel depth to 50 feet. This increase of depth is to permit the larger cargo ships access to come into the harbor without relying on the schedule of the tides. In order for that channel depth increase, the CSS Georgia needs to be removed from its sunken position and moved to a salvagable location for furture use. U.S. Navy divers will need to take exceptional caution because of the strong likelihood that live ammunition and powder are still inside the wreckage. Risk Management Planning The program manager directing the slavage project group and the project stakeholders will, in accordance with ATOM (David Hillson, 2012), assure that the risks are recognized, and peoperly managed through the lifecycle of the salvage project....

Words: 703 - Pages: 3

Premium Essay

Lessons from Valujet 592

...materials. The ramp agent conferred with the Co-Pilot about the cargo, as well he should have known the limitations of their certification. Flight 592 took off. Six minutes later there were signs of instrument failure and one minute later the last message was recorded on the flight recorder, "Completely on fire". (3) What are the key issues? What central problems and dilemmas for the field does it emphasize? In my opinion, based on the information in the article Lessons of ValuJet 592, there were many contributing factors to the crash. The low budget, corner cutting airline run by apathetic executives who profits before safety is but one. The FAA inspectors that helped develop an environment of “normalized deviation” in an effort to facilitate the growth of the company by not enforcing FAA regulations. The problem however is how as public servants tasked with maintaining public safety do we support emerging markets while maintaining oversight. It is a fine line. “Public agencies are pushed and pulled in many directions simultaneously. It is therefore especially important for public managers to be able to balance and reconcile conflicting objectives” (Cropf, 2008). This is where the FAA agents went awry. They put business before their constituents. (4) How does the case relate to public administration? In the case of ValuJet 592 shows the impact of deregulation of the airlines. The FAA was tasked with 2 objectives. One, ensuring the adherence to......

Words: 1192 - Pages: 5

Premium Essay

Proj 420 Week 1

...PROJ 420 WEEK 1 A+ Graded Tutorial Available At: http://hwsoloutions.com/?product=proj-420-week-1 Visit Our website: http://hwsoloutions.com/ Product Description PRODUCT DESCRIPTION PROJ 420 WEEK 1, Objectives of the Risk Process: The short-term goals of the project are; • To achieve break-even in first year • To have minimum traffic of 50,000 visitors in first six months and a traffic of 20,000 visitors every month from sixth month till one year • To have the sales of minimum $10,000 in first year • To generate additional advertising revenue of $1,000 in first year. The long-term goals of the project are; • To have profit margin of 20% from 5th year onwards • To have annual sale of $80,000 from 3rd year. As the website selling ebooks is an online business, the risks associated with the business are moderate. There are some situations that presents high risk such as hacking attempts, fraud transactions, money chargebacks and customer password compromise. The tolerable risk level is moderate because investment would be made in SSL certificates to ensure Objectives of the Risk Process: The short-term goals of the project are; • To achieve break-even in first year • To have minimum traffic of 50,000 visitors in first six months and a traffic of 20,000 visitors every month from sixth month till one year • To have the sales of minimum $10,000 in first year • To generate additional advertising revenue of $1,000 in first year. The long-term goals of the......

Words: 332 - Pages: 2

Premium Essay

Proj 592 Week 3 Quiz - Three Different Sets

...PROJ 592 WEEK 3 QUIZ - THREE DIFFERENT SETS Purchase here http://devrycourse.com/proj-592-week-3-quiz-three-different-sets Product Description PROJ 592 WEEK 3 QUIZ - THREE DIFFERENT SETS INFORMATION EXPERT PROJ 592 WEEK 3 QUIZ - THREE DIFFERENT SETS Purchase here http://devrycourse.com/proj-592-week-3-quiz-three-different-sets Product Description PROJ 592 WEEK 3 QUIZ - THREE DIFFERENT SETS INFORMATION EXPERT PROJ 592 WEEK 3 QUIZ - THREE DIFFERENT SETS Purchase here http://devrycourse.com/proj-592-week-3-quiz-three-different-sets Product Description PROJ 592 WEEK 3 QUIZ - THREE DIFFERENT SETS INFORMATION EXPERT PROJ 592 WEEK 3 QUIZ - THREE DIFFERENT SETS Purchase here http://devrycourse.com/proj-592-week-3-quiz-three-different-sets Product Description PROJ 592 WEEK 3 QUIZ - THREE DIFFERENT SETS INFORMATION EXPERT PROJ 592 WEEK 3 QUIZ - THREE DIFFERENT SETS Purchase here http://devrycourse.com/proj-592-week-3-quiz-three-different-sets Product Description PROJ 592 WEEK 3 QUIZ - THREE DIFFERENT SETS INFORMATION EXPERT PROJ 592 WEEK 3 QUIZ - THREE DIFFERENT SETS Purchase here http://devrycourse.com/proj-592-week-3-quiz-three-different-sets Product Description PROJ 592 WEEK 3 QUIZ - THREE DIFFERENT SETS INFORMATION EXPERT PROJ 592 WEEK 3 QUIZ - THREE DIFFERENT SETS Purchase here http://devrycourse.com/proj-592-week-3-quiz-three-different-sets Product Description ...

Words: 495 - Pages: 2

Free Essay

Proj 592 Week 6 Quiz - Three Different Set

...PROJ 592 WEEK 6 QUIZ - THREE DIFFERENT SET Purchase here http://devrycourse.com/proj-592-week-6-quiz-three-different-set Product Description PROJ 592 WEEK 6 QUIZ - THREE DIFFERENT SET PROJ 592 WEEK 6 QUIZ - THREE DIFFERENT SET Purchase here http://devrycourse.com/proj-592-week-6-quiz-three-different-set Product Description PROJ 592 WEEK 6 QUIZ - THREE DIFFERENT SET PROJ 592 WEEK 6 QUIZ - THREE DIFFERENT SET Purchase here http://devrycourse.com/proj-592-week-6-quiz-three-different-set Product Description PROJ 592 WEEK 6 QUIZ - THREE DIFFERENT SET PROJ 592 WEEK 6 QUIZ - THREE DIFFERENT SET Purchase here http://devrycourse.com/proj-592-week-6-quiz-three-different-set Product Description PROJ 592 WEEK 6 QUIZ - THREE DIFFERENT SET PROJ 592 WEEK 6 QUIZ - THREE DIFFERENT SET Purchase here http://devrycourse.com/proj-592-week-6-quiz-three-different-set Product Description PROJ 592 WEEK 6 QUIZ - THREE DIFFERENT SET PROJ 592 WEEK 6 QUIZ - THREE DIFFERENT SET Purchase here http://devrycourse.com/proj-592-week-6-quiz-three-different-set Product Description PROJ 592 WEEK 6 QUIZ - THREE DIFFERENT SET PROJ 592 WEEK 6 QUIZ - THREE DIFFERENT SET Purchase here http://devrycourse.com/proj-592-week-6-quiz-three-different-set Product Description PROJ 592 WEEK 6 QUIZ - THREE DIFFERENT SET PROJ 592 WEEK 6 QUIZ - THREE DIFFERENT SET Purchase......

Words: 496 - Pages: 2

Free Essay

Proj 592 Study Guide

...Quiz 1 Study Guide GRADED- Five Problem and Question Quiz - To be completed by the end of week 3. This Quiz covers TCOs A, B, C, and E, Integrated Cost and Schedule Control in Project Management Chapters 1–5, and A Guide to the Project Management Book of Knowledge, fifth edition, Chapters 6 and 7. Covers Weeks 1, 2, and 3 • This quiz is worth 100 total points and includes five essay questions worth 20 points each. • You have 2 hours to finish the quiz. • Remember to save frequently, because when the time limit is reached you will be exited from the exam. • If you have any technical problems, please contact the Help Desk at 800-594-2402. Answer questions with short, direct responses. For questions which require calculations, please show your calculations. Note: Detailed solutions are required to support your response and receive credit. Partial credit may be given for student responses where work is shown. Solutions from previous sessions will not be correct. You will not be given part credit for pasting solutions from previous session quizzes. The questions and/or the numbers have changed. Topics covered: The five questions cover the following material. They will test your understanding not that you can paste a paragraph from the textbook. Explanations should be in your own words. The budgeting process. Week 2 lecture notes How do we create project budgets? Is there more than one primary process? Compare and evaluate the processes. The......

Words: 528 - Pages: 3

Free Essay

Pm 592 Course Project 1

...PM 592 COURSE PROJECT John Lawson, Mathew Freeman ENERGY EFFICIENCY INSTALLATION BUSINESS VENTURE PILOT PROJECT TABLE OF CONTENTS: Item | Page | 1.0 Executive Summary | 2 | 2.0 Project Description | 2 | 2.1 Major Activities | 3 | 2.2 Resources | 3 | 2.3 Project Milestone | 4 | 2.4 Assumptions | 4 | 2.5 Project Deliverables | 4 | 2.6 Constraints | 4 | 2.7 Risk Management | 5 | 3.0 Work Breakdown Structure | 6 | 4.0 Cost Estimates | 8 | 4.1 Cost Estimation Assumptions | 8 | 4.2 Cost & Contingency Estimation | 9 | 5.0 Financial Analysis | 11 | 6.0 Project Schedule | 12 | 7.0 References | 12 | 1.0 Executive Summary This project is a pilot project for the development of a business venture to promote the installation of energy efficiency and conservation features into homes to save home owners money through the reduction of monthly energy bill. The objective of the project is to install energy efficiency features into a home of about 2500 square feet in Atlanta, Georgia and expected to be completed within 5 months at an estimated cost of $96,558.21, using a three point estimation; and achieve about 50% savings in energy usage. The expected benefits include: * Reduced utility and maintenance costs * Increased home comfort * A healthier and safer indoor environment * Improved building durability * Ultimate increase in home value The project will begin on April 16,......

Words: 1381 - Pages: 6

HD Taking My Parents to Burning Man (2014) | épisode 5 | Daniella (Pobre Diabla) E117-118